Road Closure: Ockham Road South 19 January to 22 February 2026
Published: 26 November 2025
The work being undertaken by Surrey County Council is as follows:
S278 Works for Ada Gardens Development
Phase 1 - 19-31/01/26
Under NR Bridge (new uncontrolled crossing & kerb changes), Alongside Station Parade (Raised Zebra Crossing improvement)
Phase 2 - 01-22/02/26
North of Development (Speed Humps between East Lane and Lovelace Drive), Lovelace Drive Junction (Continuous Crossing and Resurfacing)